Concrete Slab Calculator

Short answer: a 10 × 10 ft slab at 4 inches thick needs 1.23 cubic yards (about 56 × 80 lb bags). Pick a common size below or enter your own measurements.

A worker smoothing a freshly poured concrete slab with a hand trowel
A fresh slab being finished with a hand trowel.

Calculate your slab

Common sizes (feet):

Slab thickness, strength and reinforcement

Thickness and PSI are chosen together: PSI (pounds per square inch) is the concrete's compressive strength at 28 days. A stronger mix does not change the volume — the same forms hold the same yards — it changes what the slab can carry. The table below is typical residential practice reported by industry sources, not a code table. Your local building code governs — check it before pouring, especially for driveways and anything carrying vehicles.

UseTypical thicknessTypical PSIReinforcement
Sidewalk / walkway4 inches (10 cm)3,000Mesh or fiber optional
Patio, shed base, AC pad4 inches (10 cm)3,000–4,000Mesh recommended
Driveway, passenger cars5 inches (13 cm)4,000Mesh or rebar grid
Driveway, trucks / RVs6 inches (15 cm)4,000+Rebar grid
Garage floor5–6 inches (13–15 cm)4,000Rebar grid
Heavy equipment pad6–8 inches (15–20 cm)5,000Heavy rebar grid, engineered design
In freeze-thaw climates, ask for air-entrained concrete at 4,000 PSI for exterior flatwork, and consider adding 1 inch to the recommended thickness. Tell your supplier the PSI when you order — ready-mix is batched to the strength you name. For a structural slab, a slab on poor soil, or anything carrying heavy loads, have a professional or your local code specify the reinforcement.

Control joints — choose where the cracks go

Concrete shrinks as it cures, so it cracks. Control joints are shallow, planned lines that give the crack a straight place to form, instead of wandering across the slab. Industry guidance from NRMCA (Concrete in Practice CIP 6, Joints in Concrete Slabs on Grade) sets the rules below.

Slab thicknessJoint spacing (24–36 × thickness)Plan on
3.5 inches7 to 10.5 ftAbout 8 ft
4 inches8 to 12 ftAbout 8–10 ft
5 inches10 to 15 ftAbout 10–12 ft
6 inches12 to 18 ft, capped at 15 ftAbout 12–15 ft

The sidewalk calculator counts joints along a walkway at the spacing you enter, using these rules as its guide.

Curing — and when you can use the slab

Curing is not drying. Concrete gains strength through hydration, a chemical reaction with water, so keeping it moist in the first days builds strength; letting it dry out too fast causes surface cracking and weaker concrete.

After the pourAbout how strongSafe for
24–48 hoursStill soft on the surfaceLight foot traffic only — do not drag tools or wheelbarrows
7 daysAbout 70% of design strengthCars and light vehicles on driveways
14 daysAbout 85% of design strengthFurniture, planters, light equipment
28 daysFull design strengthHeavy loads, sealing and polishing

Keep new concrete moist for at least 7 days — cover it with plastic sheeting, wet burlap, or a curing compound, and do not sprinkle water on the surface to make finishing easier. Protect it from freezing in the first 48 hours, and do not use de-icing salt on it in its first winter. Cold, wet weather slows curing, so wait longer before loading the slab.

Pour checklist

A repeatable order of work that prevents the most common DIY slab mistakes. Do every step before the truck arrives — once concrete starts setting, you cannot pause it.

  1. Excavate to depth. Slab thickness plus base depth plus form height. For a 4 inch slab on a 4 inch base, dig about 10 inches below final grade.
  2. Compact the subgrade. Remove sod and loose soil, then tamp or roll the native soil firm. Do not skip this on clay or recently disturbed soil.
  3. Lay and compact the base. Usually 4 inches of crushed gravel, compacted in 2 inch layers. Dampen it without leaving puddles.
  4. Set the forms. Stake every 4 ft, check level, and slope the slab about 1/4 inch per foot away from buildings.
  5. Place the vapor barrier and reinforcement. 6 mil poly sheeting under interior slabs; raise mesh or rebar on chairs so it sits inside the slab, not on the ground.
  6. Pour and screed. Pour from the far end working back, screed level with the forms, and work continuously so you do not leave a cold joint.
  7. Float, edge and joint. Float once the water sheen disappears, edge the perimeter, and cut or tool control joints at the spacing in the table above.
  8. Finish and cure. Broom finish for traction outdoors, or trowel for smooth interior work. Cover and keep moist for at least 7 days, as in the curing table above.

Shopping list — worked example: a 10 × 10 ft patio at 4 inches

Quantities below are for this one example only. Use the calculators for any other size — the concrete and gravel volumes follow the same math, and reinforcement follows your plans and local code.

ItemFor this 10 × 10 ft patio
Concrete1.23 cubic yards net (1.36 with 10% waste), or 62 × 80 lb bags from the order volume
Gravel base (4 inches, compacted)1.23 cubic yards net (1.36 with 10% waste), about 3,670 lb of gravel
Wire mesh (or rebar)2 sheets, 5 × 10 ft each (6 × 6 grid) — overlap the joint by one grid square and trim to fit, so check your layout and allow a spare sheet on larger slabs. Or use rebar: see the Rebar Calculator.
Form boards and stakesPerimeter 40 ft: five 8 ft boards (or four 10 ft boards), 2 × 4 for a 4 inch slab, plus about 10 stakes — one every 4 ft — and screws or nails
Vapor barrier (interior slabs)About 110 sq ft of 6 mil poly sheeting — the 100 sq ft slab area plus overlap at seams and edges
Sealer or curing compoundAbout 1 gallon for one coat — coverage runs roughly 200–350 sq ft per gallon depending on the product and the surface, so check the label; allow a second gallon if two coats are recommended
ToolsScreed board, bull float, hand float, edger, joint tool, broom, shovels, wheelbarrow or mixer, tamper or plate compactor, level, tape measure, string line
Mesh sheets are commonly sold 5 × 10 ft (50 sq ft each) in a 6 × 6 grid; other sizes exist, so check what your store stocks before counting sheets. Mesh holds cracks together — it does not replace structural rebar where a design calls for it. Keep mesh or rebar raised on chairs so it sits inside the slab, not on the ground.

Pouring in hot or cold weather

The guidance below follows published industry practice (NRMCA and Quikrete). Weather changes timing, not the volume — but it decides whether the slab cures strong or cracks.

Ordering ready-mix

Suppliers often round a ready-mix order up to the next quarter cubic yard — for example, a calculated 2.61 cubic yards becomes a 2.75 yard order — and charge a delivery or short-load fee on small loads. Ask about both before you order: the price fields on this calculator accept your quoted price per yard, and any delivery fee should be added to the total separately. The cost guide lists the other fees to ask about.

Common slab sizes

SlabAt 4 inAt 6 in
10 × 10 ft1.23 cubic yards · 56 × 80 lb bags1.85 cubic yards · 84 × 80 lb bags
12 × 12 ft1.78 cubic yards · 80 × 80 lb bags2.67 cubic yards · 120 × 80 lb bags
20 × 20 ft4.94 cubic yards · 223 × 80 lb bags7.41 cubic yards · 334 × 80 lb bags
24 × 24 ft7.11 cubic yards · 320 × 80 lb bags10.67 cubic yards · 480 × 80 lb bags

Volumes are net (before waste). Bag counts use the 0.60 cu ft yield per 80 lb bag, rounded up.

Frequently asked questions

How many cubic yards for a 10×10 slab?

At 4 inches thick: 1.23 cubic yards net (1.36 with 10% waste), or about 56 × 80 lb bags net (62 with waste).

How thick should my slab be?

4 inches for patios, walkways and shed floors; 5–6 inches for driveways and garage floors carrying vehicles. Check your local code.

How many bags for a 12×12 slab?

At 4 inches thick: 1.78 cubic yards net, about 80 × 80 lb bags (88 with 10% waste).

How far apart should control joints be?

24 to 36 times the slab thickness, capped at 15 ft — about 8 to 12 ft for a 4-inch slab. Cut joints at least one-quarter of the thickness deep, and at least 1 inch deep.

How long before I can drive on a new slab?

Light foot traffic in 24–48 hours, cars after about 7 days, and full strength at 28 days. Keep the concrete moist for at least 7 days.

What else do I need to buy for a slab?

Besides concrete: a gravel base, reinforcement (mesh or rebar), form boards and stakes, and — for interior slabs — 6 mil poly sheeting, plus sealer or curing compound. The slab page lists quantities for a 10 × 10 ft patio example.