Concrete Curb Calculator

Short answer: a 50 ft long, 6 × 6 inch curb needs 0.46 cubic yards — about 23 × 80 lb bags with 10% waste. Enter your curb below.

Crushed gravel base levelled inside wooden formwork with a wheelbarrow nearby
Gravel base levelled inside the forms.

Calculate your curb

Enter measurements in the selected units. Results are shown in cubic yards and bags.

How the calculation works

A straight curb is a rectangular prism: volume = length × height × width, with length in feet and height and width in inches divided by 12, then divide cubic feet by 27 for cubic yards.

Worked example: a 50 ft curb, 6 in high and 6 in wide = 50 × 0.5 × 0.5 = 12.5 cu ft = 0.46 cubic yards net. With 10% waste: 0.51 cubic yards, about 23 × 80 lb bags.

Method note: this calculator covers straight rectangular curbs. Rolled curbs and curb-and-gutter profiles are shaped, not rectangular — measure their cross-section area and multiply by the length, or use the cubic yard calculator with that area times the length. Curb size, reinforcement and base follow your local road or driveway standards.

Common curb sizes (per 10 ft run, net)

Curb sizeVolume80 lb bags
6 × 6 in0.09 cubic yards5
6 × 8 in0.12 cubic yards6
8 × 8 in0.16 cubic yards8
8 × 12 in0.25 cubic yards12

Volumes are net (before waste). Bag counts use the 0.60 cu ft yield per 80 lb bag, rounded up.

Frequently asked questions

How much concrete for a 50 ft curb?

A 6 × 6 inch curb, 50 ft long, needs 0.46 cubic yards net (0.51 with 10% waste), about 23 × 80 lb bags.

How do you calculate concrete for a curb?

Multiply length × height × width, with height and width in feet, for cubic feet, then divide by 27 for cubic yards. Add 10% for waste.

Does this calculator cover curb and gutter?

No. Curb-and-gutter profiles are shaped, not rectangular. Measure the profile's cross-section area and multiply by the length, or use the cubic yard calculator with that area times the length.